Location:
Sewer Relining for Apartments in Kidston Street, Ascot
Timeframe:
Estimated 2 days - completed in 1.5 days
Description:
A pole installation contractor bored a post hole through a sewer pipe for a new electrical pole. The sewer was 1.6m deep under the concreted-in post and as a result, a section of the apartment’s earthenware sewer pipe was completely destroyed, leaving a 500mm gap filled with rubble.
We cleared the blockage with the use of our Robotic Cutter to clear out the more stubborn debris, then installed a 2.2m x 100mm structural Magma Flex Glass liner in place.
Services Used
Challenges:
Large amounts of builder’s rubble, bricks and broken pipe kept falling into the pipeline route – which took perseverance to remove ready for relining.