Stormwater Rehabiliation in Redbank Plains
Timeframe:
We scheduled 8 days and completed the job in 6.5 days!
Description:
The scope of the job was to rehabilitate reinforced concrete (RC) stormwater pipes by both inversion and patch relining.
The Numbers
4 x 375mm diameter patches x 1m long
20 x 450mm diameter patches x 1m long
19m x 375mm Inversion Liner (a single seamless liner to repair multiple joints)
Services Used
Challenges:
Many of the patches were done between manholes in a busy road – we organised traffic control and set up gazebos on the road to enable fast and efficient work.
The relining needed to be assessed, organised and scheduled with a fast turnaround, so the client’s roadways could be sealed to prevent erosion and the roads were sealed on time!